Washington UTC policy statement on how electric utilities serve large loads like data centers
Washington Utilities and Transportation Commission · No. UE-260162 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as open
The Washington commission opened a docket in April 2026 to develop a policy statement on how investor-owned electric utilities connect large loads, including data centers. A draft policy statement says utilities should create a separate large load customer class, using a 50 MW threshold.
From the docket: “Facilitation of a Commission-led workshop series on large load interconnections and tariffs.”
Official title: In the Matter of Proceeding to Develop a Policy Statement Addressing Electric Large Load Customers
Terms for large users, as proposed
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 50 MW | “LLC classification, the Commission believes that a threshold of 50 MW is appropriate.” Source |
| Also | Customers over 20 MW with load factor above 75 percent are presumed large load customers. | “factor of greater than 75 percent is an LLC, even if the capacity-only criterion is not met.” Source |
Who is taking part
Public Counsel Unit of the Washington State Office of the Attorney General; Data Center Coalition; NW Energy Coalition; Puget Sound Energy; Avista Corporation; Amazon Data Services; Microsoft Corporation; Google LLC.
Source
- This case was compiled from the Washington Utilities and Transportation Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Docket page: “Facilitation of a Commission-led workshop series on large load interconnections and tariffs.”
- Commission press release: “the commission plans to release a policy statement about large load interconnection with electric investor-owned utilities”
- Draft policy statement issued by the commission: “LLC classification, the Commission believes that a threshold of 50 MW is appropriate.”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.