Xcel Colorado 2024 Just Transition Solicitation: large load customer contract principles and tariff

Colorado Public Utilities Commission · No. 24A-0442E · Updated Nov 23, 2026, 18:37 ET
StateColorado
Kind of caseNew plants, lines or power purchases
OpenedOct 15, 2024
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

Public Service Company of Colorado proposed nine commercial principles for new large load customers, including a 15-year minimum term and a 100 MW threshold. The Commission generally adopted them with changes, such as six months of security, and directed a large load tariff filing by January 31, 2026.

From the docket: “Public Service Company - 2024 JTS”

Official title: Public Service Company - 2024 JTS

What the commission decided

Decision C25-0747 granted the 2024 Just Transition Solicitation application with modifications, generally adopted the commercial principles with changes, and directed Public Service to make a large load tariff filing no later than January 31, 2026. · Nov 6, 2025

Terms for large users, as approved

TermWhat it saysThe document's words
Counts as a large user at100 MW“a minimum contract term of 15 years. The load threshold would be 100 MW of new or expanded” Source
Minimum contract15 years“a minimum contract term of 15 years. The load threshold would be 100 MW of new or expanded” Source
Deposit or exit termsCommission raised required security from three months to six months of anticipated bills.“increase the security commitment to six months of” Source

Who is taking part

Office of Utility Consumer Advocate; Moffat County; City of Craig; Conservation Coalition; Colorado Public Utilities Commission Staff.

Source

  • This case was compiled from the Colorado Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Docket page: “Public Service Company - 2024 JTS”
  • Commission order (Decision No. C25-0747): “Public Service to make a large load tariff filing no later than January 31, 2026.”
  • Decision page: “Phase I Commission Decision”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.