Evergy Missouri Metro and West large load tariff (Schedule LLPS) for customers of 75 MW or more
Missouri Public Service Commission · No. EO-2025-0154 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
Evergy Missouri Metro and Evergy Missouri West asked the Missouri commission to approve new large load tariffs, Schedule LLPS, covering customers of 75 MW or more. The commission's Report and Order addressed a non-unanimous stipulation, to which Staff objected, and Evergy West later filed the tariff.
From the docket: “Case No. EO-2025-0154”
Official title: In the Matter of the Application of Evergy Metro, Inc. d/b/a Evergy Missouri Metro and Evergy Missouri West, Inc. d/b/a Evergy Missouri West for Approval of New and Modified Tariffs for Service to Large Load Customers
What the commission decided
The commission issued a Report and Order on November 13, 2025, finding the stipulation's LLPS proposal, with its 75 MW threshold, definite and clear; Evergy Missouri West's Schedule LLPS tariff was issued February 5, 2026, effective March 9, 2026. · Nov 13, 2025
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 75 MW | “monthly maximum demand of seventy-five megawatts (75 MW) at any” Source |
| Must pay for at least | 80% of contracted demand | “Minimum Demand - Minimum Demand shall be 80% of the annual Contract Capacity.” Source |
| Minimum contract | 12 years | “transitional load ramp period plus twelve (12) years” Source |
| Deposit or exit terms | Collateral equal to two years of minimum monthly bills. | “provide collateral in an amount equal to two (2) years of” Source |
Who is taking part
Data Center Coalition; Nucor Steel Sedalia; Velvet Tech Services; Google LLC; Sierra Club; Renew Missouri; Ameren Missouri; Liberty (Empire District Electric).
Source
- This case was compiled from the Missouri Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission order: “Case No. EO-2025-0154”
- Commission order: “clear eligibility threshold of 75 MW, that is even broader than the minimum 100 MW”
- Filed tariff (Schedule LLPS): “monthly maximum demand of seventy-five megawatts (75 MW) at any”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.