PNM seeks approval of amended data center power contract with Greater Kudu, plus three power deals

New Mexico Public Regulation Commission · No. 25-00048-UT · Updated Nov 23, 2026, 18:37 ET
StateNew Mexico
Kind of caseContract with a large customer
Openedn/a
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

PNM asked the New Mexico commission to approve an amended special service contract with Greater Kudu LLC, three purchased power agreements and three energy storage agreements to serve an expanding data center, along with amended Rate 36B and Riders 47 and 49. The case was on the commission's December 18, 2025 consent agenda.

From the docket: “SPECIAL SERVICE CONTRACT WITH GREATER KUDU LLC, THREE”

Official title: IN THE MATTER OF PUBLIC SERVICE COMPANY OF NEW MEXICO'S APPLICATION FOR APPROVAL OF AN AMENDED SPECIAL SERVICE CONTRACT WITH GREATER KUDU LLC, THREE PURCHASED POWER AGREEMENTS PURSUANT TO 17.9.551 NMAC, AMENDED RATE NO. 36B, AMENDED RIDER NO. 47, AND AMENDED RIDER NO. 49

What the commission decided

A Commission final order in Case No. 25-00048-UT made PNM's 3rd Revised Rider No. 47 (Green Energy Rider) effective December 18, 2025; the passages do not state the ruling on the contract itself. · Dec 18, 2025

Terms for large users, as approved

TermWhat it saysThe document's words
Counts as a large user at10 MW“The customer must achieve a minimum demand of 10,000 kW” Source
AlsoGreen Energy Rider customer must keep an annual load factor of at least 60 percent.“The customer must maintain an annual load factor of at least 60%” Source